Power Generation in Nigeria

Power sector in Nigeria boosts of about 14,541MW maximum capacity. The hydro power stations contribute about 1,976 MW (13.5%), renewable energy source Solar contributes about 1,080MW to the national grid (7.42%) and Gas/Thermal plants contribute combined capacities of 11,485MW (78.98%).

At the moment, the country power demand is estimated to be minimum of 25,000MW, however Nigeria currently has about 40% distribution capacity of its generation i.e less than 5,500MW even if the power stations worked at 100% capacity.

In line with the existing policy reforms, Nigeria targets 40,000MW generating capacity by 2020 and will need to spend approximately $10bn per annum on the power sector for the next 10 years to achieve this.

DISCO Collection Efficiency

According to NERC 2022 quarterly report, collection efficiency of Discos improved to 73.33% efficiency. The total revenue collected by all DisCos in
2022/Q4 was ₦243.65 billion out of ₦332.28 billion billed to customers which represents a +1.10 pp increase compared to 2022/Q3 (72.23%).

Relative to 2022/Q3, the total billing and total collections increased: billing increased by ₦40.62 billion (+13.93%) and collections increased by
₦32.98 billion (+15.65%). : In 2022/Q4, out of a total invoice of ₦219.24.

Servpay.ng provides a digital platform where electricity consumers in Nigeria can make electricity payments instantly. This solution increases accessibility. Click here to get started.

4th Quarter 2022 DISCO  Invoices and Payments

Credit-NERC 2023

In 2022/Q4, out of a total invoice of ₦219.24 billion issued to NBET by GenCos, NBET only invoiced ₦188.74 billion1to DisCos to accommodate the lack of cost-reflectiveness of tariffs for some.

The ₦30.50 billion not invoiced to DisCos is classified as tariff shortfall, payable to NBET by the Federal
Government for direct payment to the GenCos.

Credit- NBET 2023

January 2023  DISCO Invoices and Payment

As reported by NBET, Discos’  expected  overall  payment  performance (based  on  the  Minimum  Remittance  Order  by NERC)  is  89.22%  but overall  DisCo  payment performance achieved  at the time  of generating  this  report  is  59.01%  representing  66.14%  of  the  MRO  requirements.

With  the implementation  of NERC’s  order  on Regulatory  Net‐Offs,  only  Yola  DisCo  satisfied  the  requirements  of  the  Minimum  Remittance  Order.

Subsequent Payments are  expected  from DisCos  with  outstanding MRO  payments.

2022 Last Quarter Power Generation Breakdown

Credit- NBET 2023

Published by

Ogunsola Rotimi

An Entrepreneur, Civil Engineer, Project Manager and an Advocate of a Better Society..

Leave a Reply

Your email address will not be published. Required fields are marked *